Skip to content

// analysis

Housing in Europe: the cost of waiting for a building permit

Open the documentsThe source documents

The documents cited in the analysis and, where identified, their associated passages. An automatically detected association is not a verified claim.

Illustration for the analysis: Housing in Europe: the cost of waiting for a building permit
Sources and reading context

Topics

dated revision: November 20, 2026primary sourcesno tracker
Contents6 sections

In Madrid, a developer can start certain works while the city is still examining the technical file. An initial permit settles the key planning requirements. The review continues alongside the work and, if the final permit is refused, the developer may have to reverse work already done. The arrangement raises a practical question. How much does an extra month cost when the land is already financed and the project is waiting to break ground? S09

On 16 November 2026, the European Commission presented a study it commissioned from Intellera Consulting and Finland’s VTT research centre. It plans to use the findings in a housing simplification package due in the second quarter of 2027. Planning decisions remain largely in the hands of national and local authorities. The study identifies ways to coordinate approvals and give applicants a more predictable timetable. S01 · S02

The formal review starts with a complete file

Under the standard French rules, the review period is two months for a permit to build a single-family home and its ancillary structures and three months for other building permit applications. The period starts when the administration receives a complete application. Preparing the file, some exchanges with the planning authority and steps after the decision sit outside that period. Different deadlines can apply depending on the project and its location. S06

Applicants in the Commission’s study reported a median of about 13 weeks for formal review of a new building. For new buildings, the median for the full administrative process was about 43 weeks, including steps after the decision. Work can already be under way at that stage. The two medians cover different parts of a process that varies from one project to the next. S01

Timelines for a new building Separate medians as reported by permit applicants: 13.03 weeks for formal review and 43.45 weeks for the full process. The full process includes post-decision steps, some of which can take place during construction. Timelines for a new building Applicant survey · March to May 2026 Median weeks 0 10 20 30 40 50 Formal review 13.03 Full process 43.45 The full process includes post-decision steps.
Timelines for a new building Separate medians as reported by permit applicants: 13.03 weeks for formal review and 43.45 weeks for the full process. The full process includes post-decision steps, some of which can take place during construction. Timelines for a new building Applicant survey · March to May 2026 Median weeks 0 10 20 30 40 50 Formal review 13.03 Full process 43.45 The full process includes post-decision steps.
FIG. 01Reported medians from a survey of 204 applicants. The figures cover two separate scopes. The number of valid responses for each median is unavailable.Sources · Commission, Table 3-8

Survey coverage is uneven. Portugal provided 137 of the 226 responses from authorities, while Italy accounted for 88 of the 204 applicant responses. The surveys give an insight into the participants’ experience. Ranking national performance would require comparable projects and a more balanced sample. For developers, uncertainty also matters. A late request for documents can disrupt a financing schedule or a booking with a contractor. S01

Interest keeps accruing while a project waits

Property carrying costs start once capital is committed. Take a project that has already drawn €1 million at a hypothetical annual rate of 5%. If the balance stays constant, six months cost €25,000 in simple interest and a year costs €50,000. This illustration leaves out fees, repayments and compounding.

Interest on €1m of debt Simple interest on €1 million of drawn debt at a constant balance. At an illustrative annual rate of 5%, six months cost €25,000 and twelve months €50,000. The two other illustrative rates are 3% and 7%. Interest on €1m of debt Illustrative scenario · interest in € thousands 0 50 100 150 0 6 12 18 24 Months 3% 7% 5% At 5% 6 months · €25,000 12 months · €50,000
Interest on €1m of debt Simple interest on €1 million of drawn debt at a constant balance. At an illustrative annual rate of 5%, six months cost €25,000 and twelve months €50,000. The two other illustrative rates are 3% and 7%. Interest on €1m of debt Illustrative scenario · interest in € thousands 0 50 100 150 0 6 12 18 24 Months 3% 7% 5% At 5% 6 mo · €25,000 12 mo · €50,000
FIG. 02l0g simple interest calculation, assuming a constant balance on fully drawn debt. The rates are illustrative. The calculation excludes fees, taxes and interest compounding.

Land, studies and deposits may all be financed long before a sale. Calculating the actual interest bill requires knowing how much the developer borrowed at each stage. Some of the Commission study’s simulations estimate the time saving using the eventual value of the project. Those estimates are a model of opportunity cost under assumed financing conditions. S01

For a project with little margin for error, a few more months of expenses can force a change in the financing plan. For lower costs to show up in home prices, developments still need to start, builders need to compete and homes need to reach the places where people want them. Where buildable land is scarce, some of the gain can end up in the land price. S01 · S12

Madrid lets part of the work start earlier

Madrid’s licencia básica has a statutory decision period of one month. Once granted, it allows the specified work to proceed while the city reviews the rest of the project. The developer bears the risk that the final licence will be refused. The reform lets work and assessment run in parallel while retaining checks before the building can be used. S09

For cases processed without a collaborating body, the city’s evaluation shows average processing time falling from 177 to 139 days between the two cohorts it examined. The city attributes most of the fall to adding faster initial licences to the average. In the route involving a collaborating body, processing time rose from 40 to 49 days. Following comparable projects through to completion would show how much time residents actually gained. S10

The Commission study also looks at how information moves between departments. A PDF can be filed remotely. A digital building model, known as BIM, makes the information reusable. Staff can check floor area and levels against one version of the project, provided that the model, applicable rules and public databases can work together. The study’s scenarios illustrate how much that might help under those conditions. S01 · S02

French permits and starts follow different timetables

From October 2025 to September 2026, France’s statistical service for sustainable development estimates that 377,834 dwellings were authorised and 318,419 were started, excluding Mayotte. The totals use monthly series adjusted for seasonal and working-day effects. A start may follow a permit issued before the period. Counting the projects still waiting would require tracking each permit through to the start of work or cancellation. S04 · S05 · S13

From permit to construction In France excluding Mayotte, rolling 12-month totals for dwellings authorised and started are separate flows that cover different cohorts. Latest point, September 2026: 377,834 dwellings authorised and 318,419 started. From permit to construction France excl. Mayotte · rolling 12-month total Authorised 377,834 Started 318,419 Sept. 2026 Thousands of dwellings 0 150 300 450 600 2018 2020 2022 2024 2026
From permit to construction In France excluding Mayotte, rolling 12-month totals for dwellings authorised and started are separate flows that cover different cohorts. Latest point, September 2026: 377,834 dwellings authorised and 318,419 started. From permit to construction France excl. Mayotte · rolling 12-month total Authorised 377,834 Started 318,419 Sept. 2026 Thousands of dwellings 0 150 300 450 600 2018 2020 2022 2024 2026
FIG. 03Estimates dated to the actual event and adjusted for seasonal and working-day effects. Each point covers twelve months. Permits and housing starts refer to different cohorts. Release of 28 October 2026.Sources · SDES, September results · Statinfo 864

In October, developers surveyed by Insee were more pessimistic about buyers’ access to finance and the outlook for housing starts. Across the euro area, the ECB reports that residential investment fell 1.3% in the second quarter of 2026 from the previous quarter. Permits continued to recover, partly because permits had been registered early in the Netherlands ahead of a change in legislation. Buyer financing still matters after a project has permission to proceed. Our investigation into how French mortgages are funded follows that side of the market. S07 · S11

Completion is the test that matters

In Auckland, Ryan Greenaway-McGrevy and Yun So estimate that, in 2024, rents on new private tenancies were 23% below the level they would have reached without the reform in the authors’ preferred model. Observed rents rose over the period, and the result depends on the choice of comparison cities. Auckland had broadened building rights across large areas, changing the scope for new housing on a different scale. S08

Europe could measure the benefits of reform more directly by tracking each project from the complete application to completion. An initial licence shows when certain work can begin. The time to the start of construction, and then to occupancy, would show whether simpler procedures change the date a home becomes available. S01 · S13

Sources were consulted on 20 November 2026. SDES’s September release page is dated 28 October. Its next release, covering construction through October, is scheduled for 27 November. The cover is an AI-generated editorial illustration. S04 · S15

Sources

  1. S01 · Commission européenne / Intellera / VTT · Published: 2026-11-05 · Accessed: 2026-11-20Study of residential building permits in the EU
    Passages and scope

    Table 3-8 on p. 28 for medians, pp. 134–140 for survey coverage and pp. 176–182 for costing methods. The Commission gives 5 November as the publication date. The Publications Office record is dated 26 October. Download the official PDF.

  2. S02 · Commission européenne · Published: 2026-11-16 · Accessed: 2026-11-20Study announcement and plans for the simplification package
    Passages and scope

    Coordination and digitalisation proposals, with the package planned for the second quarter of 2027.

  3. S04 · SDES · Published: 2026-10-28 · Accessed: 2026-11-20Housing construction through September 2026
    Passages and scope

    Release page for France excluding Mayotte. Estimates by date of event and notes on the Sitadel methodology.

  4. S05 · SDES / Sitadel · Publication date not stated · Accessed: 2026-11-20Statinfo 864, tables and methodology
    Passages and scope

    Monthly authorisations and starts adjusted for seasonal and working-day effects. l0g calculates the rolling totals. Published estimates do not track outstanding permits, cancellations or time to start.

  5. S06 · Service Public / DILA · Publication date not stated · Accessed: 2026-11-20Building permits and standard French review periods
    Passages and scope

    Guide checked by DILA on 13 February. Standard periods from receipt of a complete application, with exceptions.

  6. S07 · BCE / ECB · Published: 2026-11-12 · Accessed: 2026-11-20Economic Bulletin 7/2026, residential investment
    Passages and scope

    Section 2. Real residential investment in the second quarter, developments in permits and early registrations in the Netherlands.

  7. S08 · Ryan Greenaway-McGrevy et Yun So · Published: 2026-07-11 · Accessed: 2026-11-20Rents for new tenancies after Auckland’s zoning reform
    Passages and scope

    Sections 4.3 and 4.4. The estimate is relative to a modelled scenario without reform and depends on the choice of comparator areas.

  8. S09 · Ayuntamiento de Madrid · Updated: 2026-11-10 · Accessed: 2026-11-20Basic and final licences, Articles 44–47
    Passages and scope

    Version dated 10 November. Decision period, permitted works, liability, consequences of final refusal and first occupancy requirements.

  9. S10 · Ayuntamiento de Madrid · Publication date not stated · Accessed: 2026-11-20Final evaluation of the 2022 ordinance
    Passages and scope

    Report dated 17 October 2025. Printed pages 11–12. A city evaluation of its own reform. 2021 and 2023 cohorts, with decisions through May 2022 and May 2024 respectively.

  10. S11 · Insee · Published: 2026-10-23 · Accessed: 2026-11-20October survey of property developers
    Passages and scope

    Views on housing start prospects and buyers’ access to finance. These balances are survey responses.

  11. S12 · OCDE / OECD · Published: 2021 · Accessed: 2026-11-20Housing governance and land-use planning
    Passages and scope

    Chapter 8 of Brick by Brick. How land restrictions and local governance shape the supply response.

  12. S13 · SDES · Publication date not stated · Accessed: 2026-11-20Sitadel methodology
    Passages and scope

    Definitions of authorisations and declared starts, and distinctions between reporting dates.

  13. S15 · SDES · Publication date not stated · Accessed: 2026-11-20Calendar of statistical releases
    Passages and scope

    Construction results through October are scheduled for 27 November 2026.

This analysis is not investment advice.

// cite this analysis

l0g, “Housing in Europe: the cost of waiting for a building permit”, l0g.fr, published November 20, 2026, updated November 20, 2026, https://l0g.fr/en/analysis/housing-permits-cost-of-waiting-europe-2026/


$ cd ../analysis