// analysis tool · v1.0.0
Thermal-discharge threshold selector
The rule is public. Its activation depends on the plant, date and grid context.
Five French nuclear plants. No scenario predicts river temperature, reactor safety or biological response.// l0g tool
Which thermal limit applies?
Choose a plant, date and grid context. The tool returns published rules. It does not decide whether RTE needs the unit or predict the actual ecological effect.
This tool describes a published rule. It does not forecast river temperature, future compliance, reactor safety or biological response.
Method and limitations
The rule engine applies a selected set of public EDF and ASNR prescriptions for five sites. An RTE requirement activates the permanent second tier where available. The temporary Bugey decision can only be selected from 12 to 20 July 2026 and only when RTE requires reactors 4 and 5. Consolidated legal texts and operator measurements remain the legal and operational reference.
Sources: EDF Open Data, ASNR July 2025 technical note and ASNR decision 2026-DC-052.
- EDF Open Data, thermal-discharge thresholds and limits
- ASNR, thermal discharges during summer periods, July 2025
- ASNR decision 2026-DC-052, 10 July 2026
Model v1.0.0 · 2026-08-20